CIP Monthly Status Report – May 2017

Digester
The Headworks Improvements and New Headworks projects advertised a Request for Qualifications. The Cogeneration Facility Project reached the 30 percent design milestone, submitted an air permit application, and authorized an early work package to procure the internal combustion engines and gas purification equipment. The Fiber Optic Connection Project advanced through the Substantial Completion stage gate. The San José City Council approved a master consultant agreement for on-call industrial hygienist services and awarded the construction contract for the Headworks Critical Improvements Project. Council also accepted the July-December 2016 CIP Semiannual Status Report.

Alternatives analysis work continued for the Filter Rehabilitation, Nitrification Clarifier Rehabilitation, Facility-wide Water Systems Improvements, Digested Sludge Dewatering, and Aeration Tanks Rehabilitation projects. Design work continued on the Advanced Facility Control and Meter Replacement, Blower Improvements, and Cogeneration Facility projects. The Blower Improvements Project team recommended incorporating value engineering changes into the design, which will generate net savings of approximately $3.6 million to bring the project back within budget.

Major construction continued across multiple work areas for the Digester and Thickener Facilities Upgrade, Plant Instrument Air System Upgrade, Construction Enabling Improvements, and Iron Salt Feed Station projects.

CIP Monthly Status Report – May 2017
View All CIP Monthly Status Reports
Facebook Twitter Google Plus Email

Other News in Environment