CIP Monthly Status Report – May/June 2019

Cogeneration Main Generator Building roof truss installation
In May, the 96-Inch and 87-Inch Settled Sewage Pipe Rehabilitation Project passed Stage Gate 5: Authorization to Bid. The project will repair two critical, large-diameter pipes that convey primary effluent to the secondary treatment process.

The City advertised the Nitrification Clarifiers Rehabilitation – Phase 1 Project for bid and held two mandatory bid meetings for prequalified contractors.

In June, the Construction-Enabling Improvements Project passed Stage Gate 7: Substantial Completion, and the City issued the Notice of Completion and Acceptance for the project. The Digester Gas Compressor Upgrades and Emergency Diesel Generators projects both passed Stage Gate 8: Final Acceptance.

The Digester and Thickener Facilities Upgrade Project contractor installed PVC linings in Digesters 7 and 8 to protect the concrete structure from corrosion, and they continued preparation work for the seismic ring beams’ final concrete pours.
  
The Cogeneration Facility Project design-builder installed roof trusses and a bridge crane in the main generator building.

The Blower Improvements Project contractor completed demolition of existing structures in Building 40 and the Tertiary Blower Building.

CIP Monthly Status Report – May 2019
CIP Monthly Status Report – June 2019
View All CIP Monthly Status Reports
Facebook Twitter Google Plus Email

Other News in Environment

Electrify_NewsFlash.jpg

Bay Area Home Electrification Expo

Posted on: September 12, 2019
Blue drop-off bin for unwanted or expired medicine.

Meds in the Bin, We All Win!

Posted on: September 16, 2019
Digester 16 elevated gas line

CIP Monthly Status Report – July 2019

Posted on: September 9, 2019