Subject: CONVENTION CENTER EXPANSION JOINT
COUNCIL DISTRICT: 3
Report on bids and award of contract for the Convention Center Expansion Joint Replacement Project to the low bidder, and approval of a 15 percent contingency. CEQA: Exempt.
The Department of Conventions, Arts and Entertainment has requested the Department of Public Works to replace the expansion joints in the Convention Center’s exhibit halls. The covers over the existing expansion joints have been damaged due to heavy forklift traffic. After ten years of use and maintenance, the joint covers are beyond repair.
There are three joints totaling 730 feet to be replaced between the three exhibit halls. This project, however, includes replacing just one of the joints, for approximately 250 feet of expansion joint and fire barrier and will determine how quickly contractors can repair a specific length of expansion joint. This project is scaled down in order to accommodate the time constraints imposed by the Convention Center’s schedule. Future projects will replace the remaining two joints.
The scope of work of the proposed project includes installing a new joint cover flush with the adjacent concrete floor, increasing the wheel load capacity and maintaining the original joint movement capability.
ANALYSIS
The bids for this project will be received on May 10, 2001. A supplemental memorandum will be forthcoming after bids are received. This placeholder memorandum is submitted to expedite the award to allow time to custom fabricate the material because of the exhibit hall’s limited availability.
A 15 percent contingency is requested for any unforeseen conditions which may arise during construction of this project. This contingency percentage is a little higher than usual based on the relatively low value of construction compared to the number and value of unknowns involved in replacing the joints.
This project was listed on the City's Internet Bid Line and advertised in the San José Mercury News and San José Post Record. Bid packages for all Department of Public Works construction projects are routinely provided to a standard list of various contractor organizations, builder's exchanges and disadvantaged business organizations, including United Minority Business Enterprises and the San José Minority Business Development Center.
This project was coordinated with the Departments of Conventions, Arts and Entertainment, and the Offices of Equality Assurance, Risk Manager, and the City Attorney.
1. COST OF RECOMMENDATION: Engineer’s Estimate $100,000
2. COST OF PROJECT:
Project Development $ 4,000
Construction 100,000
Design & Construction Management 35,000
Contingency 15,000
TOTAL $154,000
3. SOURCE OF FUNDING: 450 – Redevelopment Agency
4. ESTIMATED START DATE OF CONSTRUCTION: August 5, 2001
5. ESTIMATED COMPLETION DATE OF CONSTRUCTION: August 24, 2001
Fund: 450 - Redevelopment Capital Projects Fund
APPN: 6854
R.C.: 114823
Amount: $817,000
Budget
Document: 2000-2001 Appropriation
Ordinance Section 20.05, Page 11, Item 3(z23)
NONDISCRIMINATION
The City of San José Nondiscrimination Requirements are
included in this project as required by Chapter 4.08 of the San José Municipal
Code.
CEQA
Exempt.
RAJEEV BATRA
Acting Director, Public Works Department