Subject:     TUERS-CAPITOL GOLF COURSE-ADDITIONAL PROJECT COSTS

 

COUNCIL DISTRICT: 7

 

 

RECOMMENDATION

 

It is recommended that the City Council:

 

A.  Adopt the following Appropriation Ordinance amendments in the General Fund:

1.      Increase the Tuers-Capital Golf Course project appropriation by $2,967,000.

2.      Reduce the Future Capital Projects Reserve by $2,967,000.

B.   Approve an increase in the construction project contingency by $676,000, from $875,000 to $1,551,000.

C.  Adopt a resolution authorizing the City Manager to negotiate and execute an amendment to the Grow-in Agreement with San Jose Golf, LLC, a California limited liability company, modifying the term of grow-in of the Tuers-Capitol Golf Course to commence on May 1, 2001, extending the agreement term for an additional eight (8) months to terminate on March 1, 2002, and increasing total compensation to an amount not to exceed $2,513,000.

D.  Adopt a resolution authorizing the City Manager to negotiate and execute an amendment to the Operations and Maintenance Agreement with San Jose Golf, LLC regarding Rancho del Pueblo Golf Course to allow the Class A Golf Course Superintendent for the Tuers-Capitol Golf Course to also oversee maintenance of Rancho del Pueblo plus other related changes.

 

BACKGROUND

 

On August 8, 2000, City Council awarded a contract for the construction of an 18-hole golf course on a 180-acre site located northwest of the intersection of Tuers Road with Capitol Expressway. When completed, the facility will be an 18-hole, executive (par 68) golf course with a two-story, lighted driving range, clubhouse, cart barn, maintenance facility and parking.

 

The construction project is currently approximately 60 percent complete. Turf seeding of the site began on May 9, 2001. The turf development period, called “grow –in”, is expected to take ten months from the date the final turf element of the course is turned over to the prospective operator.

 

Since the beginning of construction of the golf course, several issues including, but not limited to mitigations, relocations and utilities have surfaced requiring additional effort on City staff’s part to bring them to a resolution. As a result, it has now been determined that actual costs to complete the project will be higher than the budgeted amount requiring Council approval of additional funding.

 

ANALYSIS

 

A.        Summary of Additional Project Costs

 

Additional project costs have been identified totaling $2,967,000 (see Attachment). Funding is being requested for this project to cover additional construction costs, construction management and consultant expense, PG&E expenses, habitat mitigation costs and trail paving costs, additional grow-in costs, additional FF&E and inventory costs, and initial facility operations.

 

The $2,967,000 is comprised of the following additional project costs:

 

      Additional Construction Costs                                                              $    552,000

      Department of Toxics Substances Control Voluntary Cleanup

            Agreement                                                                                             50,000

      Additional Design and Construction Management Expenses (DPW)            120,000

      Additional Costs for PG&E                                                                       180,000

      Additional Consultant Fees                                                                        275,000

      Regional Trail Paving                                                                                 300,000

      Additional Habitat Mitigation Installation                                                     165,000

      Consulting Biologist                                                                                     70,000

      Additional Grow-in                                                                                    828,000

      Additional FF&E                                                                                       175,000

      Additional Inventory (Golf Shop and Concessions)                                       47,000

      Working Capital (for facility operations)                                                       75,000

      Pre-Opening (one month’s operations/maintenance funding

            prior to opening facility to public)                                                         171,000

      Grand Opening Event                                                                                  25,000

      Liquor License                                                                                             60,000

      Site Security                                                                                                50,000

      Mitigation Area Maintenance (for 10 years)                                                           0   *

 

                                                                        Sub-total                            $3,143,000

      Deduction for project’s remaining budget (as of 5/14/01)                     (    176,000)

 

                                                                        Total                                  $2,967,000

 

*The amount for mitigation area maintenance for the next ten-year period will be unknown until a consulting biologist is retained and develops the maintenance standards for the mitigation areas.

 

The project costs indicated above are estimates based on an evaluation of the project related to construction and operations impacts. The project was originally designed concurrent with the preparation of the environmental document. Therefore, consistent with the City’s construction estimating policy, the project cost estimate were less precise than the current estimates as all of the potential project delay and additional costs could not be anticipated. Since these new estimates are expected to have a higher level of precision than early project estimates, they have a relatively small level of expected variance.

 

B.        Approval an Increase to the Construction Project Contingency

 

At the time of contract award, a construction contingency was approved for $475,000.  In March, the City Council approved a contract change order (No. 3) related to the relocation of the Wildlife Center of Silicon Valley and increased the overall project construction contingency to $875,000. 

 

Staff requests authorization to increase the project construction contingency by $676,000. This amount combined with the remaining funds in the current budget (176,000) will fully fund additional project construction work as discussed in the attachment, and the paving of the regional trail. 

 

C.        Amendment to the Agreement with San Jose Golf, LLC

 

In the original project budget, $360,000 was estimated for a six-month grow-in.  Since that time, it has been determined that a ten-month grow-in will be required.  The operator has estimated the cost for labor and materials to perform the entire ten-month grow-in at $1,188,000. Additional funding is needed in the amount of $828,000 to fund the entire grow-in period.

 

The original FF&E funding also provided $1.1 million for equipment acquisition.  Additional FF&E funding of $175,000 is requested for the balance of equipment acquisition.

 

Additionally, staff is proposing to include $50,000 for additional site security during this critical grow-in period.

 

In summary, the proposed amendment to the Agreement with SJG would: modify the commencement date to May 1, 2001, extend the term of grow-in of the course to ten months, increase the total compensation to a total amount not to exceed $2,513,000 (the total of grow-in, FF&E and site security funding), and make any changes necessary to implement the other provisions of this memo approved by City Council.

 

D.        Approval of First Amendment to Operations and Maintenance Agreement (Rancho del Pueblo)

 

Currently, the Operations and Maintenance Agreement with San Jose Golf, LLC for the Rancho del Pueblo Golf Course requires the operator to have an on-site Class B Golf Course Superintendent supervised by a Class A Golf Course Superintendent.

 

During negotiations of the operations and maintenance agreement for the new 18-hole golf course, San Jose Golf proposed that a Class A Golf Course Superintendent be allowed to oversee maintenance of both the 18-hole golf course and 9-hole golf course. This is acceptable as long as the Manager of the 9-hole golf course maintains two (2), full-time Foremen on the maintenance staff.

 

The proposed First Amendment would acknowledge the Manager’s Class A Golf Course Superintendent of the Tuers-Capitol Golf Course would also oversee Rancho del Pueblo Golf Course maintenance. Additionally, it would require two, full-time Foremen on the Rancho del Pueblo maintenance staff. The Manager will provide qualifications for this position classification to be attached to the amendment as an exhibit.

 

The Class A Golf Course Superintendent is expected to spend 35% of the position’s annual hours overseeing Rancho del Pueblo maintenance.

 

If for some reason, negotiations are not concluded successfully with San Jose Golf for operations and maintenance of the 18-hole golf course, the golf course superintendent requirement at Rancho del Pueblo would revert to the original contract language.

 

PUBLIC OUTREACH

 

Prior to development of the new 18-hole course, Public Outreach occurred through numerous community meetings conducted by Vice Mayor George Shirakawa, in addition to the environmental review and project permitting processes, and the Public Art artist selection process.

 

COORDINATION

 

This memorandum has been coordinated with the City Manager’s Office, City Manager’s Budget Office, City Attorney’s Office, and Departments of Finance; and Parks, Recreation and Neighborhood Services.

 

BUDGET REFERENCE

 

An Appropriation Ordinance amendment is proposed to fund the additional costs from the Future Capital Projects Reserve. No other commitments have been made against this reserve at this time.

 

SUMMARY

 

Additional unfunded project costs (construction, grow-in and operations) have been identified totaling $2,967,000 that require funding in order to open the facility to the public. This report provides a description of the reasons for the additional project costs and a recommended funding source.

 

The Operations and Maintenance Agreement with the operator of the 18-hole golf course will be presented in the Council in fall 2001 for approval.

 

 

NANCY JOHNSON

Director, Conventions, Arts and Entertainment

 

RAJEEV BATRA

Acting Director, Public Works Department

 

 

Attachment

 

 


 

ATTACHMENT

 

Basis for Additional Project Costs

 

Additional Construction Costs ($552,000)

 

At the time of award a construction contingency for this project was established in the amount of $475,000 or 3.4% of the construction amount.  This percentage is exceedingly low for a project of this size and complexity however, based on the knowledge and history of the site it was felt to be appropriate. Projected additional construction costs in the amount of $552,000 are now anticipated.

 

While there are numerous issues to the project, which resulted in additional costs, there are three major items that resulted in the bulk of these costs. The three items include changes and delays by PG&E to the installation of electrical facilities for the course, delays and higher costs associated with the construction of the bridge crossing Coyote creek, and impacts associated with the relocation delays of the Wildlife Center of Silicon Valley.

 

PG&E delay: Negotiations with this utility company have been difficult and time consuming. Given the financial difficulties and the loss of experienced personnel by PG&E obtaining an agreement and scheduling PG&E to complete their work has taken dramatically longer than originally envisioned. This delay has resulted in a negative impact to the project schedule and specifically to the completion of the clubhouse.

 

Bridge Crossing:  Since the work on the environmental documents, the Master plan and the construction documents were processed in parallel, it was assumed that the project would be awarded in June 2000 when the  EIR and Master plan were finally approved. But since there was a legal challenge to the EIR, project award was delayed until August 2000. This delay in award affected the installation of the bridge across Coyote Creek. Since the bridge was integral to other aspects of the construction schedule, broader areas of the project were impacted.

 

Relocation of the Wildlife Center of Silicon Valley: One of seven community groups or facilities to be relocated from the golf course site this group has been the most difficult to relocate.  Due to special operational requirements associated with a facility of this nature it was difficult to identify a suitable relocation site and define a reasonable scope of work. The relocation was completed on May 23, 2001 and will now allow the completion of holes 13 and 14.

 

Department of Toxics Substances Control Voluntary Cleanup Agreement ($50,000)

 

This Agreement would provide for Department of Toxics Substances Control (DTSC) oversight of City cleanup of lead contaminated soil found on the golf course site. Obtaining DTSC approval of the City’s proposal to cap the lead contaminated soil minimizes the risk that DTSC might order the City to do other future work to address the lead contamination. In order to obtain DTSC oversight, the City must agree to fund DTSC’s costs. The costs associated with this agreement are estimated at $50,000.

 

Additional Design and Construction Management Expenses (DPW) ($120,000)

 

Since the contractor, project management firm and architect will be involved in the project longer than anticipated, Public Works staff will also be required for a longer duration to oversee their work and additional funding will be required. The additional funding requested for Public Works staff costs is 120,000.

 

Additional Costs for PG&E ($180,000)

 

The project budget had an allowance of $110,000 for PG&E for electrical and gas utility services.  The actual fees for the service agreement with PG&E exceeded this estimate by approximately $180,000. The agreement was approved and the fees paid on April 20, 2001, in order to facilitate on-going construction and minimize delays to the construction project. The additional fees were paid out of other items in the project budget to facilitate construction.

 

Additional Consultant Fees ($275,000)

 

As noted above, completion of the project construction will take longer than anticipated. The services of the construction management firm (Heinbuch Golf Construction), design consultants (JMP Golf Design Group) and environmental consultant (Denise Duffy & Associates) will still be required through the completion of the construction work. The environmental consultant is also providing supplemental services in reviewing the mitigation plans for consistency with the project Environmental Impact Report (EIR).

 

Additional funding for these continued and supplemental services are requested in the amount of $275,000.

 

Regional Trail Paving ($300,000)

 

A regional trail along Coyote Creek is part of a long-range plan of the City. The master plan for the golf course identifies the portion of the trail that is contiguous with the golf course as part of the overall plan for development of the site. This trail will connect the existing trail terminus at Tuers Road and Capitol Expressway with Stonegate Park, completing another link in the long-range plan.

 

The golf course construction contract included the grading of the trail only. The paving of the trail was not included in the bid for the project at the time of award. It was anticipated that the cost for paving the trail would be identified from a source other than the bond revenues that pay for the golf course construction contract.

 

Completion of the trail is part of the project as defined in the master plan for the golf course. The trail will need to be completed consisted with the trail construction practices for recreational and commuter purposes. A portion of the trail also is required to support vehicle access to the driving range area for San Jose Municipal Water to service its wellheads. It is recommended that the paving be completed before the next winter rains, which may contribute to erosion of the graded dirt trail. The estimated cost to pave the trail is $ 300,000.

 

Additional Habitat Mitigation Installation ($165,000)

 

The project budget had an allowance of $350,000 for the installation of a habitat mitigation plan. Plans for the mitigation installation were developed after the certification of the EIR, approval of the golf course master plan and construction contract award. The plans are now 95% complete with an estimated cost for installation of $515,000. Therefore, the additional habitat mitigation installation costs are $165,000.

 

Consulting Biologist ($70,000)

 

As a requirement of the mitigation area plantings, the City must ensure these areas are maintained and monitored for a ten-year period. A consulting biologist will prepare maintenance standards and perform the ten years of monitoring. The estimated cost for the consulting biologist to perform both is $70,000.

 

Additional Grow-in ($828,000)

 

As required in the project EIR, a Water Quality and Chemical Application Management Plan (CHAMP) was developed by Questa Engineering (Questa) to identify key water quality issues and how they were to be handled during golf course construction and maintenance.

 

The CHAMP sets forth-reasonable standards for a mature golf course, but did not completely take into account the grow-in phase for the course. According to estimates, grow-in of the course at the original CHAMP levels could take approximately 18-24 months. A joint proposal was submitted to the City by Mr. Terry Buchen, the City’s agronomist overseeing grow-in of the golf course, and the proposed operator. This proposal was forwarded to Questa. The joint proposal calls for extending the originally-estimated, six-month grow-in to ten (10) months provided that certain adjustments are made to the CHAMP’s nutrient level allowances.  The joint proposal has been approved by Questa.

 

The lengthening of the course grow-in adds to its cost. At the time the bond issue was calculated, the grow-in period was budgeted at $360,000 and anticipated to take six months.  The current budget for the entire grow-in period (ten months) is estimated at $1,188,000 requiring an additional $828,000.

 

Additional FF&E ($175,000)

 

As part of the project bond issue, $1.1 million was financed for FF&E acquisition.

 

The current budget for the entire FF&E acquisition is estimated at $1,275,000 requiring an additional $175,000.  This $175,000 provides funding for additional maintenance equipment, and other office, café and driving range equipment.

 

Additional Inventory for Golf Shop and Concessions ($47,000)

 

Additional inventory funding for the golf shop and concessions areas is needed to augment the original funding for inventory of $40,000. This will provide a total of $87,000 for initial inventory.

 

Working Capital ($75,000)

 

Working capital funding in the amount of $75,000 is needed to provide funding to cover months during which golf course expenses are greater than revenues. Since the operator is managing the golf course on behalf of the City, all revenues and expenses are those of the City. Therefore, there needs to be sufficient funding to accommodate months (primarily winter) where revenues will be insufficient to cover operating costs in the initial years.

 

Pre-Opening ($171,000)

 

Pre-opening funding is to provide resources to the operator in the amount of $171,000 for staff-up and training of the golf shop, food and beverage and administrative staff, utilities and supplies and materials. It also includes funding for marketing of the facility.

 

Grand Opening Event ($25,000)

 

A grand opening event is planned for the facility and is an unfunded need. The requested amount to fund this event is $25,000.

 

Liquor License ($60,000)

 

Originally, only a beer and wine license was anticipated for the food and beverage operation at the course. However, the operator is being requested to obtain a liquor license. Funding in the amount of $60,000 is requested for acquisition of this license.

 

Site Security ($50,000)

 

The golf course site with its significant riparian corridor was undeveloped for a number of years with easy access by the public. It has been used for informal recreational activity, getting from one side of the creek to the other, homeless encampments, illegal dumping, arson and other types of activity.

 

Site security funding will provide for continual fence repairs and a security patrol during the evening and early morning hours, among other measures during the grow-in period.

 

Mitigation Area Maintenance

 

Mitigation area maintenance costs are unknown at this time. The maintenance standards for the mitigation areas will be prepared by a consulting biologist retained by the City to do the long-term monitoring of the site. After preparation of the maintenance standards, the golf course operator, and other firms if necessary, will be asked to provide a cost proposal for performing these services.