CITY OF SAN
JOSÉ, CALIFORNIA Department of
Planning, Building and Code Enforcement 801 North First
Street, Room 400 San José,
California 95110-1795 |
Hearing
Date/Agenda Number C.C.:
11-06-01 Item |
|
|
|
File Number PDC01-08-083 |
|
|
STAFF REPORT |
Application Type Conforming Planned Development Rezoning |
|
|
|
Council District 4 |
|
|
|
Planning Area North San Jose |
|
|
|
Assessor's
Parcel Number(s) 09725068 |
|
|
PROJECT
DESCRIPTION |
Completed by: EL |
|
|
Location: West side of
North First Street, either side of Component Drive |
||
|
Gross Acreage: 40.92 |
Net Acreage: 40.92 |
N/A |
|
Existing
Zoning:: IP(PD) |
Existing Use:
Vacant |
|
|
Proposed
Zoning: IP(PD) |
Proposed Use: Research and
Development/Offices |
|
|
GENERAL PLAN |
Completed by: EL |
|
|
Land
Use/Transportation Diagram Designation IP Industrial Park |
Project
Conformance: [x] Yes [ ] No [ ] See Analysis
and Recommendations |
|
|
SURROUNDING LAND
USES AND ZONING |
Completed by: EL |
|
|
North: Industrial,
Hotel, Retail I
Industrial and A(PD) Planned Development Zoning
Districts |
||
|
East: Industrial I
Industrial Zoning Districts |
||
|
South:
Industrial I Industrial and Heavy
Industrial Zoning Districts |
||
|
West: Industrial
and Vacant
I Industrial, HI Heavy Industrial and A Agricultural Zoning Districts |
||
|
ENVIRONMENTAL
STATUS |
Completed by: EL |
|
|
[x]
Environmental Impact Report found complete November 12, 1987 [ ] Negative
Declaration circulated on |
[ ] Exempt [ ]
Environmental Review Incomplete |
|
|
FILE HISTORY |
Completed by: EL |
|
|
Annexation
Title: Orchard No. 69 |
Date: April 26,
1977 |
|
|
PLANNING
DEPARTMENT RECOMMENDATIONS AND ACTION |
||
|
[x] Approval [ ] Approval
with Conditions [ ] Denial |
Date: _________________________ |
Approved by: ____________________________ [ ] Action [ ]
Recommendation |
|
APPLICANT/DEVELOPER |
OWNER |
|
|
Frank Jesse BEA Systems, Inc. 2315 North First Street San Jose, CA
95131 |
Frank Jesse BEA Systems, Inc. 2315 North First Street San Jose, CA
95131 |
|
|
PUBLIC AGENCY
COMMENTS RECEIVED Completed by: EL |
|
Department of
Public Works See Attached |
|
Other
Departments and Agencies Municipal Water, Fire Department, CPTED Program, Environmental Services, State of California Department of Transportation, Santa Clara Valley Transportation Authority, and County of Santa Clara. |
|
GENERAL
CORRESPONDENCE |
|
None received |
|
ANALYSIS AND
RECOMMENDATIONS |
BACKGROUND
The applicant, BEA
Systems, Inc. is requesting to a conforming Planned Development Rezoning from
IP(PD) Planned Development Zoning District to IP(PD) Planned Development Zoning
District to allow a height increase from 90 to 105 feet along the portion of
the site that fronts North First Street for research and development/office
uses. Minor text modifications are also
proposed to reflect traffic improvements that have been already completed and
revised Zoning Ordinance requirements for bicycle/shower facilities.
A Planned
Development Zoning (PDC93-05-017) for this 40.92 gross acre site was approved
by City Council on March 1, 1994, permitting research and development uses and
establishing a height limit of 90 feet for the portions along North First
Street.
The project site is
generally surrounded to the east, west, south and north by industrial
uses. There are some minor hotel and
commercial uses to the northeast of the site, mainly to provide support for the
predominantly industrial uses in the area.
ENVIRONMENTAL REVIEW
The environmental impacts of this project
were addressed by a Final EIR entitled, "Rincon de Los Esteros
Redevelopment Plan," and findings were adopted by City Council Resolution
No. 60197 on November 12, 1987.
GENERAL PLAN CONFORMANCE
The proposed
conforming rezoning to IP(PD) Planned Development Zoning District is consistent
with the San José 2020 General Plan Land Use/Transportation Diagram designation
of IP Industrial Park.
ANALYSIS
The key issue
associated with this rezoning is consistency with the overall goals and
objectives of the Planned Development (PD) Zoning previously approved by the
City Council in PDC93-05-017. The PD
rezoning proposes to increase the maximum height of buildings from 90 to 105
feet and some minor text modifications.
The two modifications include changes to the traffic mitigation and the
number of required bicycle/shower facilities from the original zoning
Height Change
The previously
approved PD Zoning provides for approximately 3 million square feet of research
and development/office uses proximate to the light rail corridor and to the
North San Jose employment center. The
proposed conforming rezoning would maintain the previously approved total
square footage on the project site, but would allow the applicant to take
advantage of a recently approved General Plan Amendment that raised the maximum
height of buildings along the transit corridor to 120 feet. The proposed height change would allow the
developer to reconfigure his site and building designs to build along North
First Street to a height of up to 105 feet without adding square footage. This proposed height limit change will bring
the zoning for this development into conformance with the General Plan and will
be consistent with the City’s policies for industrial development, without
lessening the overall quality of the project.
The proposed land uses will not be modified from those previously
approved and the reconfiguration will facilitate the development of industrial
uses consistent with City policy along transit corridors.
The proposed
conforming PD rezoning will remove the traffic mitigation required in the
original zoning that have already been completed by either the current property
owner (BEA Systems, Inc.) or the previous developer (Agilent Technologies). There are two traffic mitigations that will
still be required and kept in the new PD rezoning. The two remaining traffic mitigation requirements are:
1. North First Street and Component
Drive. Provide an additional left-turn
lane on the west leg.
2. De La Cruz/Trimble. The Trimble Bridge Project will provide
temporary restriping to add an eastbound and westbound through lane. A contribution in the amount of $100,000
shall be paid towards the ultimate construction of the eastbound and westbound
lanes.
The plan set as
submitted by the applicant, attached to this staff report, lists a different
mitigation in the place of the second requirement mentioned above. The applicant’s submittal requires the
developer to provide an additional left-turn lane along De La Cruz Boulevard
and Trimble Road. The applicant will be
required to submit revised plans that removes the requirement to build the
left-turn lane and replace it with the requirement to provide a contribution
instead, as stated in the paragraph above and per the direction from the
Department of Public Works.
The Department of Transportation, VTA and the County of Santa Clara
comments request a new Transportation Impact Analysis (TIA) for this
project. The Department of Public Works
and planning staff have determined that because this project does not propose
new square footage for this project, a new TIA is not necessary. The rezoning will allow a change in the
building configuration and architecture only and therefore, will not create
additional traffic impacts. The traffic
impacts for this project were already analyzed and appropriate mitigation
identified during the original zoning (PDC93-05-017) for this project site, and
do not need to be updated. These
agencies have been notified of this determination.
The required
number of bicycle/shower facilities has been modified in the conforming PD
rezoning to reflect the requirements adopted in the most recent update to Title
20 of the San Jose Municipal Code or Zoning Ordinance, dated February 19, 2001.
Staff has determined that the proposed
modification of the PD Zoning is minor and will not jeopardize the City’s
overall objectives for the site, and can be supported as a conforming rezoning.
PUBLIC OUTREACH
A notice of the
public hearing was distributed to the owners and tenants of all properties
located within 500 feet of the project site.
RECOMMENDATION
Planning staff
recommends approval of the proposed Conforming Rezoning for the following
reasons:
1. The proposed
rezoning is consistent with the San Jose 2020 General Plan Land
Use/Transportation designation of IP Industrial Park.
2. The
proposed rezoning is compatible with surrounding land uses.
3. The
proposed rezoning will facilitate redevelopment of the subject site in
conformance with the General Plan.