CSJ  12-18-01, Item 5.5 Attachment

    PROJECT ARTIST Co Dist Funding Source Artwork 2%  Admin  Art Budget End Date  STATUS
    West Valley Library Elizabeth Conner 1 City sculptural elements  $       156,000  $       23,400  $       132,600 2003  design development
    Edenvale Park/Hayes Mansion TBD 2 City/Bonds TBD  $       413,885  $       82,777  $       331,108 2004  artist selection
    2nd/San Fernando:Block 2 TBD 3 Private mural  $       750,000  $     112,500  $       637,500 2002  on hold/project funding
    4th/San Fernando Garage Cork Marcheski 3 City neon elevators  $       753,180  $     115,800  $       637,380 2002  fabrication
    Adobe/Phase II TBD 3 Private TBD  TBD        on hold/project funding
    Bernal Park TBD 3 City TBD  $         16,000  $         2,400  $         13,600 2002  on hold/staffing
    Boston Properties/Plaza de Almaden James Carpenter 3 Private glasswork  $     1,000,000  $     200,000  $       800,000 2003  artist selection
    Boston Properties/Plaza de Almaden TBD 3 Private TBD  $     1,000,000  $     200,000  $       800,000 2003  on hold/base project
    Center for Performing Arts Artworks David Middlebrook  Sam Richardson  Benjiamino Bufano 3 City sculpture placement  $       150,000  $             -    $       150,000 2001  on hold/staffing
    Civic Center/streetscape Andrew Leicester/TBD 3 City Streetscape elements  $     1,000,000  $     150,000  $       850,000 2004  schematic design
    Civic Center/water feature Doug Hollis/Anna Murch 3 City water feature  $     2,650,000  $     397,500  $    2,252,500 2004  schematic design
    Concert Hall Jun Kuneko 3 RDA TBD  $       740,000  $     111,000  $       629,000 TBD  on hold/funding
    Fallon Statue sculpture base 3 RDA sculpture  $               -    $             -    $               -   2001  foundation design
    Guadalupe River Park TBD 3 RDA concrete enhancement TBD     TBD on hold/funding
    Horace Mann School Seyed Alavi 3 RDA sculptural elements  $       100,000  $       15,000  $         85,000 2003  fabrication
    Joint Library Mel Chin 3 RDA integrated  $       970,440  $     145,566  $       824,874 2003  fabrication
    PROJECT ARTIST Co Dist Funding Source Artwork 2%  Admin  Art Budget End Date  STATUS
    Northside Comm Center Peter Mollica 3 City stained glass  $         30,000  $         4,500  $         25,500 2002  on hold/funding
    Northside Comm Center Diana Pumpelly Bates 3 City sculpture  $         70,000  $       10,500  $         59,500 2002  on hold/funding
    Northside Comm Center Carlos Perez 3 T.O.T. meditation garden  $         15,000  $             -    $         15,000 2002  schematic design
    Ohlone Alan Cunahan 3 RDA environment  $       184,000  $         4,000  $       180,000 2001 fabrication
    Olinder Neighborhood Association* Carlos di Silva, Erik Irquidi, Juan Raul 3 T.O.T. mural  $           9,000  $             -    $         15,000 2001  fabrication
    Paseo Villa Condominiums Ned Smyth 3 Private mosaic mural  $       243,000  $       40,200  $       202,800 2001  design development
    Post Street Alison Sky 3 RDA streetscape  $       600,000  $       90,000  $       510,000 2002  schematic des
    Transit Mall TBD 3 City TBD  $       270,000  $       40,500  $       229,500 2002  on hold/staffing
    Twohy Building TBD 3 Private sculpture  $       100,000  $       20,000  $         80,000 TBD  artist selection
    Alviso Library Donna Billick 4 City mosaic  $         40,000  $         6,000  $         34,000 2001  design development
    Berryessa Branch Library TBD 4 Bonds TBD  $       200,114  $       30,017  $       170,097 2004  artist selection
    Berryessa Community Center** John Pugh 4 C & C mural  $               -    $             -    $         55,750 2001  fabrication
    Mabury Park Steve Gilman 4 City TBD  $         57,750  $         2,000  $         55,750 2002  master plan
    RiverOaks Diana Bates, Deborah Kennedy 4 City gate, threshold  $         33,000  $             -    $         33,000 2002  on hold/land issues
    Mexican Cult Hert Center Ann Chamberlain Victor Zaballa 5 RDA gates, mosaics  $       300,000  $       45,000  $       255,000 TBD  on hold/staffing
    Pala Youth Center Reis Neimi 5 RDA entry elements  $         97,350  $       14,603  $         82,748 2003  schematic design
    Parque de la Amistad TBD 5 City TBD  $         12,000  $         1,800  $         10,200 TBD  on hold/staffing
    Alam/Almaden median* TBD 7 T.O.T. TBD  $         15,000  $             -    $         30,000 2002  artist selection
    Animal Shelter Lewis de Soto 7 City entry elements  $       182,000  $       27,300  $       154,700 2003  design development
    PROJECT ARTIST Co Dist Funding Source Artwork 2%  Admin  Art Budget End Date  STATUS
    Capital Tuers Golf Course Michael Davis 7 City water elements & seating  $       200,000  $       30,000  $       170,000 2002  fabrication
Tully Road Branch Library TBD 7 Bonds TBD  $       191,000  $       28,650  $       162,350 2005  artist selection
    Groesbeck Hill Park Glen Rogers 8 City TBD  $         13,600  $         1,350  $         12,250 2002  schematic design
    Lake Cunningham Park TBD 8 City TBD  $         67,000  $       10,050  $         56,950 TBD  on hold/staffing
    Meadowfair Park/Phase II Cynthia Handel 8 City seats  $         12,000  $         1,800  $         10,200 2001  base project delay
    Welch Park Barbara Abbott 8 T.O.T. sculpture  $         12,750                 -    $         12,750 2001  fabrication
    Blossom Hill Branch Library Deborah Merksy 10 Bonds entry elements  $       178,025  $       26,704  $       151,321 2004  schematic design
    Airport Projects/Yr 1 TBD CW City TBD  $       500,000  $       75,000  $       425,000 2002  base project delay
    Airport/Master Plan The Rome Group CW City Art Plan  $         75,000  $             -    $         75,000 2001  planning
    Kelley Park TBD CW City TBD  $         71,000  $       10,650  $         60,350 TBD  on hold/staffing
    TOTAL:          $13,478,094  $2,076,566  $11,478,278    
    City: CIP projects                  
    RDA: Redevelopment projects                  
    T.O.T: Transient Occupancy Tax                  
    C&C: Construction and Conveyence Tax                  
    Bonds: Bond projects                  
                       
    NOTE: *= additional community funds; ** = non-2% project