Subject:     ALMADEN BOULEVARD SANITARY SEWER REHABILITATION PROJECT

 

COUNCIL DISTRICT:  3

 

 

RECOMMENDATION

 

Report on bids and award of contract for the Almaden Boulevard Sanitary Sewer Rehabilitation Project to the low bidder, Wesco Infrastructure Technologies, in the amount of $683,105, and approval of a contingency in the amount of $69,000.  CEQA:  Exempt.

 

BACKGROUND

 

The Almaden Boulevard Sanitary Sewer Rehabilitation project is located on Almaden Boulevard between St. John and San Carlos Streets.  The project area is shown on the attached map.  Internal television inspection shows that this sewer suffers from moderate to severe structural deterioration due to the effects of hydrogen sulfide.  Rehabilitation measures are needed to enhance the structural integrity and serviceability of the sewer.

 

In order to maintain the sanitary sewer structural integrity, the proposed project consists of rehabilitating 30 and 33-inch diameter reinforced concrete pipe (RCP) with a Cured-In-Place Pipe liner. This is a trenchless rehabilitation method that will minimize the reduction in diameter, which maintains the capacity of the sewer.

 

Provisions have been included in the project which will restrict working hours to minimize the construction impact on traffic and inconvenience to residents.  Provisions have also been included that direct the contractor to coordinate construction activities with events at the San José Arena, Center for Performing Arts, and outdoor events held through the Office of Cultural Affairs.

 

ANALYSIS

 

Bids were received on May 10, 2001, with the following results:

 

 

 

Variance Over/(Under)

Contractor

Bid Amount

Amount

Percent

 

 

 

 

Insituform Technologies, Inc.

  (Benicia, CA)

$1,121,500

 $142,325

 14.5%

Engineer’s Estimate

    979,175

--

--

Gelco Services, Inc.

  (Salem, OR)

     944,915

   ($34,260)

  (3.5)%

Ford Construction Co., Inc.

  (Lodi, CA)

    942,305

   ($36,870)

  (3.8)%

Wesco Infrastructure Technologies

  (Torrance, CA)

         683,105

  (296,070)

(30.2)%

 

The bid submitted by Wesco Infrastructure Technologies is 30.2 percent below the Engineer’s Estimate.  The difference in price between the low bid and the Engineer’s Estimate is largely attributed to the lower than expected costs for diversion of the sewage flows required for installing the pipe liner. 

 

A contingency of $69,000, is requested for any unforeseen conditions that may arise during construction.

 

PUBLIC OUTREACH

 

This proposed project was listed on the City’s Internet Bid Line and advertised in the San José Mercury News and San José Post Record.  Bid packages for all Department of Public Works construction projects are routinely provided to a standard list of various contractor organizations, builder’s exchanges, and disadvantaged business organizations, including United Minority Business Enterprises and the San José Minority Business Development Center.

 

The San José Downtown Association will be contacted prior to construction.

 

COORDINATION

 

This proposed project has been coordinated with the National Guard, the Department of Planning, Building and Code Enforcement, and the Offices of the City Attorney, Risk Manager, Budget and Equality Assurance.

 

COST IMPLICATIONS

 

1.  COST OF RECOMMENDATION:  $683,105

 

2.  COST OF PROJECT:

 

Prior

Fiscal Year

 

Current

Fiscal Year

 

FY

2001-02

 

 

 

 

 

 

           Project Development

$7,000

 

$  10,000

 

 

           Construction

 

 

  683,105

 

 

           Design & Construction Management

 

 

    74,000

 

$169,000

           Contingency

 

 

 

 

    69,000

 

 

 

 

 

 

                                                                       TOTAL

$7,000

 

$767,105

 

$238,000

 

3.  SOURCE OF FUNDING:  540 – Sanitary Sewer Connection Fee Fund

 

4.  ESTIMATED START DATE OF CONSTRUCTION:  September, 2001

 

5.  ESTIMATED COMPLETION DATE OF CONSTRUCTION:  March, 2002

 

BUDGET REFERENCE

 

Fund:                             540

Appn:                            4130

R.C.:                              108153

Amount:                         $1,091,000

Budget Document:          2000-2001 Adopted CIP, Item No. 2, Page 568

 

CEQA

 

Exempt.

 

 

RAJEEV BATRA

Acting Director, Public Works Department