CIP Accomplishments
CIP accomplishments to date include:
-
17 projects completed, valued at $342.5 million.
-
9 projects currently in construction ($378 million)
Completed Projects
-
96-Inch and 87-Inch Settled Sewage Pipe Rehabilitation - completed February 2022; $6.4 million total; $4.4 million construction
-
Advanced Facility Control & Meter Replacement Phase 1 - completed July 2022; $12.5 million total; $6.9 million construction
-
Advanced Facility Controls and Meter Replacement Phase 2 - completed June 2023; $15.1 million total; $8.3 million construction
-
Cogeneration Facility - completed December 2020; $115 million total; $92 million construction
-
Construction Enabling Improvements – completed August 2018; $4.5 million total; $3.3 million construction
-
Digester & Thickener Facilities Upgrade - completed April 2022; $228 million total; $178 million construction
-
Digester Gas Compressor Upgrade – completed April 2017; $15 million total; $13 million construction
-
Digester Gas Storage Replacement – completed November 2015; $2.8 million total; $2.0 million construction
-
Emergency Diesel Generators – completed July 2017; $18 million total; $15 million construction
-
ESB Lab HVAC Ducting Replacement - completed November 2021; $900,000 total; $500,000 construction
-
Fiber Optic Connection – completed January 2017; $627,000 total; $254,000 construction
-
Headworks Critical Improvements – completed August 2018; $2.4 million total; $1.7 million construction
-
Iron Salt Feed Station – completed May 2018; $8.4 million total; $5.7 million construction
-
Plant Instrument Air System Upgrade – completed November 2018; $4.5 million total; $3.2 million construction
-
Switchgear M4 Replacement and G3 & G3A Removal - completed May 2022; $10.2 million total; $5.6 million construction
-
Yard Piping Improvements - Phase 1 - completed January 2022; $5 million total; $3 million construction