CIP Accomplishments

CIP accomplishments to date include: 

  • 17 projects completed, valued at $342.5 million.

  • 9 projects currently in construction ($378 million)

Completed Projects

  • 96-Inch and 87-Inch Settled Sewage Pipe Rehabilitation - completed February 2022; $6.4 million total; $4.4 million construction

  • Advanced Facility Control & Meter Replacement Phase 1 - completed July 2022; $12.5 million total; $6.9 million construction

  • Advanced Facility Controls and Meter Replacement Phase 2 - completed June 2023; $15.1 million total; $8.3 million construction

  • Cogeneration Facility - completed December 2020; $115 million total; $92 million construction

  • Construction Enabling Improvements – completed August 2018; $4.5 million total; $3.3 million construction

  • Digester & Thickener Facilities Upgrade - completed April 2022; $228 million total; $178 million construction

  • Digester Gas Compressor Upgrade – completed April 2017; $15 million total; $13 million construction 

  • Digester Gas Storage Replacement – completed November 2015; $2.8 million total; $2.0 million construction

  • Emergency Diesel Generators – completed July 2017; $18 million total; $15 million construction

  • ESB Lab HVAC Ducting Replacement - completed November 2021; $900,000 total; $500,000 construction

  • Fiber Optic Connection – completed January 2017;  $627,000 total; $254,000 construction

  • Headworks Critical Improvements – completed August 2018; $2.4 million total; $1.7 million construction

  • Iron Salt Feed Station – completed May 2018; $8.4 million total; $5.7 million construction

  • Plant Instrument Air System Upgrade – completed November 2018; $4.5 million total; $3.2 million construction

  • Switchgear M4 Replacement and G3 & G3A Removal - completed May 2022; $10.2 million total; $5.6 million construction

  • Yard Piping Improvements - Phase 1 - completed January 2022; $5 million total; $3 million construction